This is from the Southern Locomotives webpage.
"The groundwork has now been prepared for both Sidmouth and Brocklebank Line at Sellindge, with these two projects moving forward together before the former is returned to Swanage. We have now acquired our own grit blasting equipment, including an almost new cabinet blaster for smaller items. By coincidence a scaffolding firm has just rented some land for storage a few yards from our area, and have offered to organise undercover accommodation for Brocklebank Line and Sidmouth's frames for us.
We will arrange the transfer of Sidmouth's frames, but we need to have moved Brocklebank Line's first as they will sit behind Sidmouth's, as the latter's will be moving off site first. It's impractible to arrange for Sidmouth's frames to arrive on the same day as Brocklebank Line is lifted, so this will be undertaken the week after the main move.
The delays to Sidmouth's restoration are frustrating but our supporters will appreciate that it's essential to have Sir Keith Park, Eddystone, Manston and 257 Squadron earning revenue to fund much of the cost of its restoration. Given the number of shareholders supporting Sidmouth, and the relatively large amount of cash they have contributed Sidmouth will come first.
Our minor moves are taking place on 21st September and the crane is booked for the 7th October for Brocklebank Line and the 19th for Sidmouth's frames."
I believe the frames of Sidmouth was delayed slightly due to our rainy season and should be there now.