  1. The photos where posted while I was previously typing...

     

    I reckon they will use the temporary track to carry the first track panel which will then be slewed on to the cliff side. The temporary track will then be lifted and attached to the end of the first laid panel and while this is happening the second panel will be run along the cliff side track including the newly laid panel then slewed on to the seaside track. The 3rd panel will then go along the 1st laid panel and the temporary track and be slewed on to the seaside alignment next to the second panel. Temporary track then attached to the end of panel 3 and panel 4 (the second cliff side one) will move along the seaside line and be slewed across. Panel 5 will be another cliff side on that goes down panel 2&3 and temporary track before being slewed to the cliff side.

     

    This will mean the 2 panels with the used wood sleepers could end up just by the tunnel as previously speculated by others and minimised the temporary track relaying too.

     

    Suggested sequence:

    Dover - 2 - 3 - 6 - Tunnel

    Dover - 1 - 4 - 5 - Tunnel

     

    Starting with:

    Dover - temp -  -  - Tunnel

    Dover - 1 -  -  - Tunnel

     

    Dover - 2 - 3 -  - Tunnel

    Dover - 1 - temp -  - Tunnel

     

    Dover - 2 - 3 - temp - Tunnel

    Dover - 1 - 4 - 5 - Tunnel

    The only problem I can see with this is that sections 1 and 2 need to be curved and from what I can see the made up sections are straight.

×
×