An answer to my question in bold below;
Dear Christopher ****,
Thank you for contacting us to request information about the Werrington grade separation project.
Your request was passed to the project team and they have responded to say that all works are due to be completed by Christmas 2021.
The major works to the railway corridor and the operation to remove excavated material (which has seen an increase in the number of lorries) are winding down over the next month.
There will still be minor works and landscaping works throughout autumn prior to the end of the project.
I hope that you find this information helpful.
Kind Regards
Sharon Neil
Network Rail
Customer By CSS Web (Christopher ****) (30/07/2021 07.54 PM)
Could you please provide me with a timetable for the completion of the dive-under at Werrington Junction?
Regards,
Chris ****