Jump to content
Users will currently see a stripped down version of the site until an advertising issue is fixed. If you are seeing any suspect adverts please go to the bottom of the page and click on Themes and select IPS Default. ×
RMweb
 

Folkestone-Dover sea wall wash-out


Recommended Posts

  • RMweb Premium

Mmm...Interesting....

But it seems modern UK decision making has to be 'short-termist'.

A hundred years? Forget it!

Lets focus down onto forseeable cashflow....

...oh! And (to self) will I still be in this job in two years time?

 

dh

I think that that is a tad pessimistic. Many recent railway projects have been future proofed even under Railtrack. When Leeds was rebuilt around 2000 Railtrack decided to put back the double crossing from the S & C to Holbeck in case coal and other freight took off. A wise decision. When York Minster caught fire the spec for the replair materials was a minimum life of 500 years was specified ruling out Concrete. Yes we do see a lot of short termism but it is not universal.

 

Jamie

  • Like 2
Link to comment
Share on other sites

  • RMweb Gold

I think the iPhone calculation may well have been "if we don't *ever* re-open, what's the long term impact on the rest of the network/capacity/revenue/publicity..."  That would have been a big number.

 

So, being the Govt, you then look at how to do it right, for a not-unreasonable-sum, in a way that provides ~100 years of service.

 

The NR engineers will have had a lot of say - and probably worked very closely with private industry to develop a workable solution.

 

Whilst it would have been a relatively unknown geotech (as shown by the need for test holes drilled prior to real work starting), the principles would not have changed much once from the original concept - and in reality, it's just a 2016 version of the timber trestle built all those years ago - just a question of how much embedment depth to give all those piles. And in the overall scheme, a 35m pile will not cost exponentially more than a 20m pile. The extra materials would not have been much - a bit of steel and concrete - but the time to drill could have been - however as we've seen from dt's photos, they seem to drill down each hole very quickly.

 

That measure - the number of piles/day or day/pile - will have been a key calc for estimating the cost, as you multiply any work by 120+ times, you then can get a solid idea of the overall duration, which would have been the biggest risk for the contractor I'd suggest. And the biggest opportunity, too: if they planed and costed the work on averaging 4 piles a week for 30 weeks, but were able to install 6 piles a week, all of a sudden the duration drops from 30 weeks to 20, and that 10 weeks of overhead costs becomes profit...  (gains are never likely to be that large, but I used simple numbers to make a point: time=$ )

 

*edited and expanded for clarity

 

You're assuming that NR has engineers with the necessary knowledge and experience to make a fully informed decision.  Far more likely in this day and age particularly that if they wanted any sort of second guessing of what contractors etc are proposing they would have engaged consulting engineers to act on their behalf (let's face it - NR couldn't even find the drawings of the seawall design and all other relevant technical paperwork).  So - just like Dawlish - they engage specialist contractors to do the work plus contract out the design as well in all probability.

 

The real decision is that having been given some costs estimates based on what their consulting engineers have agreed is likely to be the best solution it is totally up to NR to do the sums and make the decision.  They will obviously know the daily cost of having the line closed as a very large part of it will be represented by real money they are paying to train operators etc.  They will also know the political (small 'p') pressure to not only get the line reopened but even more importantly to make sure it is reopened and they might even be able to put some money estimates against the effect of that.  They and their consulting engineers can no doubt put together a financial case for doing the job a particular way and prove that the chosen way is the best long term value and part of putting that together would be the cost of repeated closures and repairs if the job isn't don properly this time round.

 

The DfT, for all their shortcoming, would  (or at least should) be able to get a pretty fair estimate of the costs involved long term in closure of the line and its impact on the value of the franchise and that will feed into their view to which they will add the impact of both political and Political pressures (= their future in the jobs they hold).

 

So overall getting at realistic numbers - albeit with possible technical risk - isn't difficult.  The remaining question is again largely technical and centres on the duration of the works - where as much as anything it's a balance of feasibility and time (as confirmed by the consulting engineers) against the short term compensatory payments and any longer term costs.  In other words - number crunchers heaven.

  • Like 2
Link to comment
Share on other sites

  • RMweb Premium

The geologist (BSc Hons) in me says that piling through chalk will be relatively quick as it is a soft rock.  What delays the process is dewatering.  Had the chalk been packed full of flint bands as it is farther west then the time taken and materials consumed could have increased significantly as flint is one of the most resistant sedimentary rocks there is.  It's both hard and brittle meaning it flakes and chips - as any napper or stone-waller would know - but doesn't yield happily to any form or drilling.  A decent band of flint has a potential to completely mangle a piling rig's drill bit.

  • Like 2
Link to comment
Share on other sites

  Had the chalk been packed full of flint bands as it is farther west then the time taken and materials consumed could have increased significantly as flint is one of the most resistant sedimentary rocks there is.  It's both hard and brittle meaning it flakes and chips - as any napper or stone-waller would know - but doesn't yield happily to any form or drilling.  A decent band of flint has a potential to completely mangle a piling rig's drill bit.

There are some flint bands in Dover. Probably p****d off the 172nd Tunneling Company RE having it right in the middle of their tunnel.

Pic02287%20640_zpsbyootetz.jpg

 

And another old fossil too.

Pic02285%20640_zps53peswwz.jpg

  • Like 6
Link to comment
Share on other sites

I've lost count of how many bearing (as distinct from test) piles have been placed so far - are there any at all yet on the seaward side?

2

My bet is that the trimming of the head of the pile is preparation for an in-situ conc ground beam/ slab. The beam/ slab re-inforcement will have to overlap;. A problem sometimes encountered with nervous structural engineers is they don't leave enough space in between the re-inforcement bars to enable concrete aggregate to be vibrated around

dh

 

NB some lovely pics of Shakespeare cliff for a Back drop (hint hint)

  • Like 1
Link to comment
Share on other sites

I've lost count of how many bearing (as distinct from test) piles have been placed so far - are there any at all yet on the seaward side?

2

My bet is that the trimming of the head of the pile is preparation for an in-situ conc ground beam/###### slab. The beam/###### slab re-inforcement will have to overlap;. A problem sometimes encountered with nervous structural engineers is they don't leave enough space in between the re-inforcement bars to enable concrete aggregate to be vibrated around

dh

 

NB some lovely pics of Shakespeare cliff for a Back drop (hint hint)

I have been looking to chose a photo,to put into paint and encircle the said piles,with the exception of the test ones.

That's why I go to the site when there is no workings and it is tidy .

 

To date,the nearest pile seaward is the one you see being de capped today, no others have been attempted .

The majority being land ward for the first section of raft.

Also you can see the piles formed for the centreline of the 1&2 rafts.

 

NB. I am working on the staircase in the depressed area,not that I can get to be depressed so much.

I have applied for Modellers Licence, have been informed,there is a hell of a Q. Before I am granted one.

Age, does not count in seniorority terms,apparently.

 

PS. It is more akin to a building fire escape, than a cliff side staircase to a foot over bridge !

Edited by David Todd
  • Like 5
Link to comment
Share on other sites

I have been looking to chose a photo,to put into paint and encircle the said piles,with the exception of the test ones.

That's why I go to the site when there is no workings and it is tidy .

 

To date,the nearest pile seaward is the one you see being de capped today, no others have been attempted .

The majority being land ward for the first section of raft.

Also you can see the piles formed for the centreline of the 1&2 rafts.

 

NB. I am working on the staircase in the depressed area,not that I can get to be depressed so much.

I have applied for Modellers Licence, have been informed,there is a hell of a Q. Before I am granted one.

Age, does not count in seniorority terms,apparently.

 

PS. It is more akin to a building fire escape, than a cliff side staircase to a foot over bridge !

 

NB.

 

26703364052_c7902b3395_k.jpgP1380484 by David Todd 2012, on Flickr

 

 

26714551372_c71c30e1bf_z.jpg

Picture 1294 by David Todd 2012, on Flickr

Edited by David Todd
  • Like 8
Link to comment
Share on other sites

Maybe I should investigate the ipads camera ?

 

So on to the camera photo's i took today.

 

As I came over the ridge of the Western Heights, the crane's had moved, from yesterday.

 

26721076022_449b7c9099_k.jpgP1380621 by David Todd 2012, on Flickr

 

26721080212_ff8e1c2007_k.jpgP1380620 by David Todd 2012, on Flickr

 

A cruise skip is in today.

 

26542318280_04102e6bcb_k.jpgP1380618 by David Todd 2012, on Flickr

 

26541500080_3d03519de5_k.jpgP1380619 by David Todd 2012, on Flickr

 

 

We are now at the site.

 

26747477991_c91a85ef34_k.jpgP1380622 by David Todd 2012, on Flickr

 

26814593435_df18edaafe_k.jpgP1380624 by David Todd 2012, on Flickr

Edited by David Todd
  • Like 2
Link to comment
Share on other sites

Filling another drill hole.

I watched this, from 3 different position's

 

26209384024_e84008c7be_k.jpgP1380630 by David Todd 2012, on Flickr

 

26542273370_da8116736b_k.jpgP1380631 by David Todd 2012, on Flickr

 

26210218393_afece21884_k.jpgP1380655 by David Todd 2012, on Flickr

 

26209282614_6c4ed71d2f_k.jpgP1380656 by David Todd 2012, on Flickr

 

26209273354_f5a9757a50_k.jpgP1380658 by David Todd 2012, on Flickr

 

26542123840_a278abf87a_k.jpgP1380659 by David Todd 2012, on Flickr

 

26542115200_80acd5135e_k.jpgP1380662 by David Todd 2012, on Flickr

 

26747337761_dd0aa12f35_k.jpgP1380663 by David Todd 2012, on Flickr

 

26747332941_1a1887a239_k.jpgP1380665 by David Todd 2012, on Flickr

 

26210169133_741effb907_k.jpgP1380667 by David Todd 2012, on Flickr

 

26210163193_2aeb2a0166_k.jpgP1380668 by David Todd 2012, on Flickr

 

26210156513_6ef2b7066e_k.jpgP1380669 by David Todd 2012, on Flickr

 

26720881342_9b867bd317_k.jpgP1380670 by David Todd 2012, on Flickr

  • Like 4
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...